From the Village of Wellsville Department of Public Works
Our paving contractor is planning to pave on the following streets June 16, 2022:
Seneca Street from Howard Street to Chamberlain Street
Stevens Street from Howard Street to N Highland Avenue
N Highland Avenue from W. State Street to Fassett Lane.
Howard Street from Seneca Street to Stevens Street
Our paving contractor is planning to pave on the following streets June 17, 2022:
Cameron Street from E Hanover Street to Franklin Street
Franklin Street from S Main Street to Rauber Street
Franklin Street from Rauber Street to Cameron Street
Osbourn Street from E Hanover Street to the 4 lane
W Hanover Street from S Main Street to W Dyke Street
After milling and before paving, manholes and water boxes will be elevated, so please drive carefully. During paving and milling access to these streets will be limited and parking on the street will not be allowed so please plan ahead with parking arrangements to avoid any conflicts.
We thank you for your cooperation and patience. If you have any questions, please call our office at 596-1710.